产品展示
悬挂类型七
 

Suspension Type 7

Step by Step
Installation of Type 7


Before Starting the Installation

* Unpack all the components and place
them on a clean surface (mat/sheet).
Check to make sure that you have recieved
all the components specified on the enclosed
parts list. If components are missing,
contact FabricAir, Inc. immediately.

* In order to keep the FabricAir ducts clean,
handle the ducts with clean hands. Make
sure that any tools which might come in
contact with the ducts have been cleaned
before use.

* Make sure that the necessary tools are
available - see the instructions.

* Provide hardware for anchoring - see items
1 & 3 under installation sequence.

* If the ducts are to be installed in a new
building, purge the handling systems and
install the prefilter before installing the
FabricAir ducts. This is done to remove
dust, which would otherwise collect in
the FabricAir duct.

Installation Sequence

1. Install anchor (27), centered above the
duct, with the appropriate distances
shown in the drawing. Fasten the anchors
directly to the overhead surface.

2. Cut the spacer (9) into suitable lengths,
depending on the distance between the
overhead surface and the top of the rail.

3. Install the spacer (9) into the spacer ceiling
anchor (27).

4. Install anchor (27) at the end of the
spacer(9), and push the rail beyond the
installation screw in the spacer rail anchor.

5. Join rails together using joiners (6).

6. Once the rail has been installed, install
the FabricAir duct. If the duct is shorter than
30', it will normally be delivered in one
section. If the duct exceeds 30' it will
normally be divided in sections with zippers.
Put the gliders of the duct into the rail. If
the duct is divided in sections - begin with
the first section.

7. When all sections are installed in
the rail, zip the sections together.
Fasten the duct to the hem connection
on the AHU collar with the mounting
belt (17/18), and install the end cap
for H-rail (8).

Follow the above procedure for installing
FabricAir Plenum ducts. Zip the FabricAir ducts
to the FabricAir Plenum duct.


After Completing the Installation:

Always be sure to give the customer a
copy of the maintenance instructions
and information concerning mainte-
nance intervals.


 

>>点此返回